Shelly aquired a really nice shaped 82 ATC 110 and decided to do a full out restoration.Shelly's 110 is all OEM.
Here is a virtual walk through of restoring an ATC
She started by completely tearing it down to nothing. Then came sandblasting and painting everything was then re-assembled.
Here are some pictures of what she started with. Notice Shelly's SWEET!! riding boots!!!
MOST PARTS ARE FINISHED (03/05/06)
A most Productive weekend (04/09/06)
Things are working out very well for Shelly's OEM restore. Should be showroom condition in no time. All she has to do is finish re-assembling it and get the new tires. She ordered Sheng Shin 22X11X8 Knobbies (OEM look-a-likes) on Saturday morning, so they should be in and ready to mount late this week. If all goes well, we'll be "Rolling" by the coming weekend.
OH - Shelly just remembered, she needs to paint her exhaust!!!!
Things are coming together now!!! 4-15/16-06
Re-assembly has gone well, as expected. This machine is rolling. Shelly's just needs some detail cleaning/polishing on the engine and the engine put back in and she has herself a NEW 1982 ATC110 - OEM (or as close as it gets here at Tionesta Trikes). We're down to the end of this project now. I am tickled with the way is has turned out. Enjoy these pictures, as there will only be one more set, and those shall be finished pictures of this Awesome OEM Restore.
02-04-06 | 1 hour | remove tires and wheels - hang from rafters - remove seat, fenders and tank - remove air box - remove brake drum cover and axle nuts - remove front axle - remove all 3 hubs - toolbox |
02-05-06 | 3 hours | sandblast and paint: toolbox - airbox - brake drum cover - front axle and hubs |
02-08-06 | 2 hours | rear brake drum and rear axle removal |
02-18-06 | 1 hour | removed headlight - rear skid plate - foot pegs - and exhaust/muffler |
02-19-06 | 6 hours | removed axle carrier - chain plates - carb - electrical system - front clip (bars, bearings) - grab bar and tail light -rear brake mechanism and cables. Sandblasted and primed some parts listed. |
03-04-06 | 6 hours | Primed and painted all sanblasted parts |
04-07-06 | 0.5 hours | Removed Engine from frame - removed remaining electrical system |
04-08-06 | 5 hours | Sandblasted Frame and motor mounts - cleaned engine (degreased - pressure washed) - painted frame |
04-09-06 | 1 hour | Begin re-assembly |
04-15/16-06 | 6 hour | Re-assembly |
12 weeks | 31.5 hours | Labor of Love |